When entering into a contract, the US Government must first have appropriated funds to pay for the contracted goods or services. This results from the Anti-Deficiency Act (ADA), which is famous in government contracting circles as ‘the Boogeyman’ that keeps new contracting professionals awake at night. Simply put, violating the ADA is the cardinal sin of government contracting. But government processes vary in length and complexity, and the funding process is long and intricate. This means that sometimes the contracting process cannot wait on the funding process. In other cases, the government needs services of particular scope for a certain length but knows that funds are currently limited. The government personnel might be confident that additional funds will be allocated but these funds are still pending. For these instances, the FAR contains two clauses that permit the award of contracts contingent upon the availability of funding.
FAR Part 32, Contracting Financing, describes the stipulations for how contracts can be funded. More specifically, 32.706.1, Clauses for contracting in advance of funds, contains language that guides the use of these two clauses being discussed. This paragraph states “a) Insert the clause at 52.232-18, Availability of Funds, in solicitations and contracts if the contract will be chargeable to funds of the new fiscal year and the contract action will be initiated before the funds are available.” FAR Clause 52.232-18 is from April 1984, and reads as follows:
Funds are not presently available for this contract. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.
Basically, this clause allows the contracting process to play out while funds are being secured, appropriated and allocated. Any work performed by the contractor prior to notice by the Contracting Officer that funds have been made available will be done at contractor’s risk and it is possible that the contractor will not receive full pay for this work. Therefore, it is in the contractor’s best interests to fully understand this clause and why it appears in the contract, and then to not begin performance until the CO advises them that funds are now available.
The second clause addressing Availability of Funds, 52.232-19, Availability of Funds for the Next Fiscal year, is intended for use if a one-year indefinite quantity or requirements contract will be awarded, and if it is funded by annual appropriations and will extend beyond the initial fiscal year. What makes this significant is the indefinite nature of the work being performed, leading to some uncertainty in funding, as well as the duration of the contract running past the initial fiscal year. Since the funds for the subsequent fiscal year are valid for only that year and have therefore not been appropriated, the contracting officer must have a mechanism to award the contract pending receipt of the new fiscal year funds. This clause enables that action.
These clauses represent two significant means by which the FAR deals with the realities of government process in a practical manner that enables important actions to occur while remaining compliant with applicable laws and regulations.