The Prospectus Process for GSA Public Building Services

By Kevin Jans · April 25, 2021 · 4 min read

Line 18 of the Agency Forecast blog that I recently wrote leads to the GSA Prospectus/Repair, Alteration and Modernization projects for FY21 and many previous fiscal years.  The Prospectus Process is interesting and one that I became familiar with as a CS/CO for the GSA Public Building Services. If you are an Architect Engineer (AE) or Construction Firm and have interest in participating in GSA’s Capital projects (aka prospectus projects) – this is the intelligence that you need to know well in advance of the contracting for it. (https://www.gsa.gov/real-estate/gsa-properties/prospectus-library/repair-alteration-and-modernization)

Section 40 USC 3307 entitled “Congressional approval of proposed projects” lists appropriations that must be approved by Congress.  The General Services Administration (GSA) Public Building Services (PBS) is an agency that builds, maintains and leases public buildings and therefore is one of the agencies that must obtain approval for these certain projects.

What this means is that, prior to seeking appropriations, GSA is required to obtain congressional authorization for constructing, purchasing, leasing, or renovating real property. Hence, GSA must submit a Prospectus to two committees—the Senate Committee on Environment and Public Works and the House Committee on Transportation and Infrastructure—for each proposal that exceeds the then current prospectus thresh hold (currently$3.95M). The Prospectus must provide detailed information about the project, including its location and estimated cost – you will see that information in the website cited in the first paragraph.  GSA’s portfolio includes courthouses, land ports of entry, and federal office space so those are the properties that GSA contracts for.

By law, a project that exceeds the prospectus threshold will not receive appropriations unless both committees pass resolutions approving of the prospectus. The current prospectus thresh hold for Construction alteration and lease projects/alterations in leased buildings is $3.095M and has been since 2018 - but it does increase from time to time.  GSA keeps the year-to-year thresh holds on their website at: https://www.gsa.gov/real-estate/design-construction/gsa-annual-prospectus-thresholds

All of the details regarding this process for the GSA can be found in Section 02-73.35 of the Federal Management Regulation (FMR) which you can read at:  https://www.gsa.gov/cdnstatic/FMR_pdf_archive_072505.pdf

In pertinent summary, the FMR states that GSA has a prescribed method for evaluating, proposing, and securing funding for capital projects (i.e., those over the prospectus threshold). This is known as the Capital Investment and Leasing Program (CILP). The key characteristics of the program are:

• GSA Regional Offices submit annual proposals for consideration and inclusion into the GSA’s budget request to GSA’s Central Office, which develops the submission to the Office of Management and Budget (OMB). The Regional project submissions for a given authorization are sent in about two years before the fiscal funding year to allow for internal and OMB reviews. For example, projects for authorization for 2021 were submitted to GSA’s Central Office in the spring of 2018.

• GSA issues the specific requirements for project submittal in an annual Planning Call to its Regional Offices. The specific requirements for these submissions may vary slightly from year to year, but the basics remain constant.

• GSA’s Feasibility Studies and Program Development Studies (PDSs) form the foundation of the Capital Program.

• GSA typically must receive separate authorization for design and site acquisition funding (Feasibility Study) and construction funding (PDS). These actions are usually two years apart.

• GSA requires a Feasibility Study to support an authorization request for site acquisition and design funding.

• GSA requires a Program Development Study (PDS) to support an authorization for construction funding. Design/build and lease construct projects follow a different path, using

one-step funding process. In these cases, the Feasibility Study and PDS are combined into a single document.

GSA also posts the Enacted Federal budgets and updates it each fiscal year upon enactment of the public law. This is the document that posts the appropriation for the Prospectus, if/once approved by the two committees.  Once the appropriation has been authorized, the GSA can take action to contract for the repair/modernization or construction.  Therefore, if you are an AE or construction contractor, you can learn about upcoming Capital programs by monitoring these websites.

There is also a GSA video regarding this process: