The Structure of the Contract always Favors the Government

By Kevin Jans · October 18, 2020 · 3 min read

Government contracts have lots of clauses. This litany of clauses exists specifically to protect the interests of the United States (read: us, the US citizen and the taxpayer). They are not, for the most part, there to protect you, the contractor. It is important that you understand how the contracts are structured and which clauses are of specific importance to your company. Okay, technically they all are, but some will impact you more than others based on your situation. See the list of examples below of clauses that you will want to play close attention to. Understanding the key clauses that affect you is important – important enough to make it part of your bid/no bid strategy.

FAR 52.249-1 through 52.249-5: The Termination for Convenience clauses (affectionately called “T4C” for short) are designed for the government’s convenience to, you guessed it, terminated your contract. Each of these clauses are written for different situations (firm fixed price, removal of improvements, services, and others). However, all of them allow the government to terminate the contract whenever they no longer need your product or service. The good news is that when this happens, you are entitled to some costs for shutting down the work (known as “termination costs”). However, in exchange for this the government is not required to fulfill the entire contract and you need to understand that your cash flow for the remainder of the contract will no longer be available to you. Note: T4C’s are not common. However, this can be very different from a commercial contract. It’s vital that you understand the government’s ability to walk away from your contract if they no longer have funding for it, or if they have decided they don’t need the support anymore.

FAR 52.232-20 and 52.232-22: The Limitation of Cost and the Limitation of Funds clauses are designed to limit the government’s responsibility to fund your contract in the event that Congress does not provide funds beyond the initial contract award. This is particularly important on contracts with one-year money (operational items, services, etc.) that is authorized one year at a time by Congress.

Note: For more information on the impact of Congressional Appropriation rules on contracts, listen to Contracting Officer Podcast Episode 019 “What are the colors of money?"

You need to understand that neither the contracting officer nor the program manager has much control on whether Congress appropriates the money to them from year to year. Please understand that this is normally not a problem for most contracts. However, in recent years (FY2012-2017) many companies were surprised to hear that their funding was cut, and by extension, their contracts were terminated (T4C’ed). There is no guarantee of funding or that a resultant contract will be issued.  Be cautious on bidding on these contracts if you are not certain that they will be funded for the life of your contract.

There are many more examples of ways contracts are structured to benefit the government (Christian Doctrine, Government Purpose Rights, etc.). The best way to prepare for, and potentially defend against, the head start the government has on your contract is to review your clauses and floss your contract (see Contracting Officer Podcast Episode 272  “Flossing Your Contracts.”) That way, you know which clauses and contract features create the most risk for you, and what to do to be ready.