Subscribe Member Home

Trust But Verify

By Kevin Jans · January 2, 2022 · 3 min read

The Federal Acquisition Regulation (FAR) is comprised of 37 Chapters and over 2000 pages. Contracting Officers are highly trained, but there isn’t a person alive who is an expert on the FAR and Case Law. A Contracting Officer is a human being with his/her own perspective, strengths, flaws and judgement.

Therefore, when it comes to government contracting - especially contract administration – remember this Russian Proverb: Trust But Verify. Just because a CO tells you something, that doesn’t mean it’s true! And, for the grey areas in the FAR, you have to look to Case Law and/or even file a claim or protest for your specific fact pattern and/or to create new case law

For instance, a CO rejected a contractor’s equitable adjustment request under FAR 52.222-43 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment (Multiple Year and Option Contracts) because the contractor had submitted the adjustment past the 30 days cited in the clause. He thought that meant the final answer was no.

And in this case, it seems plausible, doesn’t it? Afterall, the clause states that “the Contractor shall notify the Contracting Officer of any increase claimed under this clause within 30 days after receiving a new wage determination unless this notification period is extended in writing by the Contracting Officer.” So, the CO relied upon the language in the clause – we all know that “shall” denotes the imperative.


However, in fact, there is case law that even negates the 30-day timeframe in the clause, under certain circumstances.

...In absence of express language warning that the contractor will lose rights for late submission, the Government would only be able to strictly enforce the notice provision if it can demonstrate that it was prejudiced by the delay. See Riggs Nat’l Bank of Washington, DC v. Gen. Servs. Admin., GSBCA 14061, 97-1 BCA ¶ 28,920;Air Masters Corp. v. Gen. Servs. Admin., GSBCA No. 16237, 04-2 BCA § 32,688.  The Government must demonstrate any prejudice related the contractor’s late submission. In Air Masters, the GSBCA found that the Government had not demonstrated prejudice for an untimely submission that was nearly one year late. See Air Masters Corp. v. Gen. Servs. Admin., GSBCA No. 16237, 04-2 BCA § 32,688.  Where the contract modification has not yet been implemented and any alleged delay just served as an interest free loan to the Government, it is unlikely that Government could demonstrate any prejudice....

 ...The case law has made it abundantly clear that the FAR price adjustment clause 30-day notice requirement is not interpreted strictly and that the Government can only use untimely notice under this FAR provision as an absolute defense if it can show some prejudice or has set forth some contract timeliness provision explicitly to the contrary. And any such special contract provision, to the extent it varies the standard FAR clause, arguably requires an approved FAR deviation to be operative. The FAR clause itself only requires notice in 30 days. As a general rule, that FAR provision isn’t interpreted strictly to work a forfeiture on the contractor.”

In this instance, the modification did not “set forth…contract timeliness expressly to the contrary” and it’s doubtful that they can show prejudice.  The result?  The contractor is advised to share this case law and resubmit the request.

Just like the government, you have rights and remedies under your contract. This is just one example of why you should do your due diligence in contract administration. So, if you get a “no” – trust but verify - do your own research or reach out to Skyway for some expert advice.