When is a Contract Change Out of Scope?

By Kevin Jans · February 7, 2021 · 2 min read

Sometimes, it’s difficult to determine if a change that the end user or contractor is requesting to a contract is in -scope or out- of -scope of the contract.  What is the standard, how should the Contracting Officer make the determination?  This is one of the situations in contract administration that can fall into a gray area and for gray areas, the Contracting Officer typically (or should) make a determination based on the set of facts in the issue at hand and if appropriate to the circumstance, consult their Legal Counsel.

In addition to the FAR, the CO or Legal Counsel will search GAO or one of the Courts for legal decisions and precedents on the matter.

GAO has weighed in on how to determine if a change is in or out of scope and has given some clear direction as per the excerpts below from Case B-414260, Zodiac of North America.

…CICA requires “full and open” competition in government procurements as obtained through the use of competitive procedures. 10 U.S.C. § 2304(a). …In determining whether a modification triggers the competition requirements in CICA, our Office looks to whether there is a material difference between the modified contract and the contract that was originally awarded… To assess whether a contract is so substantially changed by the modification that the original and modified contracts are essentially and materially different, we consider such factors as the extent of any changes in the type of work, performance period, and costs between the modification and the original contract, as well as whether the original solicitation adequately advised offerors of the potential for the change or whether the change was the type that reasonably could have been anticipated, and whether the modification materially changed the field of competition for the requirement…

If a CO determines that a change is in scope, they will follow the procedures in FAR 43 (Contract Modifications). However, if they deem that the change is out of scope, they will/should either create a SOW/PWS for a new requirement or they will/should issue a modification in accordance with the non-competitive procedures at FAR, 6.303, 8.405-6, or 16.505(b)(2).